Progress Chart

[ Current Projects |  Completed Projects | Future Projects ]

Approved Projects

A project is considered approved once Ministry of Education funding is committed. Normally, a public announcement by the Ministry of Education indicates support to prepare and submit a Project Definition Report (PDR). The projects on this list have received the funding required to proceed into design and construction.

This Progress Chart is updated following each board meeting.


Logo
Date of Approval
Design Complete
Tender Award
Construction
Completion*
Open for Students

#218 Regent Road Elementary

New School
27 Classrooms

Aug. 9, 2017

Completed
Awarded

96%

Sep
2022

#164 Sullivan Heights Secondary

Addition
28 Classrooms

Jul. 10, 2018

Completed
Awarded

98%

Sep
2022

#009 White Rock Elementary

Addition
8 Classrooms

Apr. 20, 2020

Completed
Awarded

91%

Dec
2022

#202 Sunnyside Elementary

Addition
10 Classrooms

Feb. 11, 2020

Completed
Awarded

87%

Nov
2022

#188 Morgan Elementary

Addition
8 Classrooms

Jun. 3, 2020

Completed
Awarded
93%

May
2023

#207 Ta'talu Elementary School

New School
27 Classrooms

Apr. 6, 2020

Completed
Awarded
17%

Jan
2025

#040 K.B. Woodward Elementary

Addition
8 Classrooms

Jun. 8, 2020

Completed
Awarded

75%

May
2023

#115 Snokomish Elementary

New School
27 Classrooms

Apr. 28, 2021

Spring
2023

Spring
2023

0%

Spring
2025

#118 South Meridian Elementary

Addition
8 Classrooms

Aug. 12, 2021

Spring
2023
Spring
2023
0%

Fall
2024

#161 Semiahmoo Trail Elementary

Addition
10 Classrooms

Aug. 12, 2021

Spring
2023
Spring
2023
0%

Fall
2024

BUILDING ENVELOPE PROJECTS





#147 Westerman ElementaryBEP

Awarded
95%Jan
2023
#160 Frost Road ElementaryBEP

Awarded64%Dec
2023
#157 Coyote Creek ElementaryBEP

Awarded5%Dec
2023







SUPPORTED PROJECTS (Pending Ministry of Education Funding Approval)
#048 Kwantlen Park Secondary
10441 132nd St.
Addition
11 Classrooms

Pending



#047 Guilford Park Secondary
10707 146th St.
Addition
18 Classrooms

Pending



#150 Tamanawis Secondary
12600 66th Ave. 
Addition
23 Classrooms

Pending



#167 Fleetwood Park Secondary
7940 156th St.
Addition
20 Classrooms

Pending



*This column represents the percentage of the contract value that has been paid out to the contractor.

Design

Following approval of the funding agreement with the Ministry of Education, the design stage begins.
Sketch plans/schematic design is the preliminary design concept. The sketch plan then advances a more detailed design, used to secure City of Surrey develop#2C82C9ment/building permits. These designs are included in the bid tender package.

Tender

When a project's design is complete, it is put to tender. Construction firms bid for the contract agreement to perform the work.

Construction

After the project has been awarded to the successful bidder, construction can begin. This stage has many varying factors that affect the amount of time required to finish a project.

Target Occupancy

In this stage the new development is ready to be furnished, fit and occupied. While the building is now being used as planned, minor work continues.