Progress Chart

[ Current Projects |  Completed Projects | Future Projects ]

Approved Projects

A project is considered approved once Ministry of Education funding is committed. Normally, a public announcement by the Ministry of Education indicates support to prepare and submit a Project Definition Report (PDR). The projects on this list have received the funding required to proceed into design and construction.

  • The completion/occupancy dates in this report are target dates only and subject to change as the projects proceed.
  • This progress chart is updated following each board meeting.

Logo
Approval
Design
Complete
Tender
Award
Construction
Completion*
Occupancy
Open for
Students

#040 K. B. Woodward Elementary

8-Classroom
Addition

Jun. 8, 2020

Completed
Awarded
100%
Sep 2023

#207 Ta'talu Elementary

27-Classroom
New School

Apr. 6, 2020

Completed
Awarded
62%
Jan 2025

#118 South Meridian Elementary

8-Classroom
Addition
Aug. 12, 2021
Completed
Awarded
9%
Spring 2025

#161 Semiahmoo Trail Elementary

10-Classroom
Addition
Aug. 12, 2021
In process
Spring 2023
5%
Winter 2024

#115 Snokomish Elementary

27-Classroom
New School

March 30, 2021

In process
Summer 2023
0%
Spring 2026
20-Classroom
Addition
Feb 22, 2023
In process
Spring 2025
0%
Fall 2027
23-Classroom
Addition
May 9, 2023
In process
Fall 2025
0%
Spring 2028
18-Classroom
Addition
May 26, 2023
In process
Fall 2025
0%
Spring 2028

BUILDING ENVELOPE PROJECTS





#157 Coyote Creek
Elementary
BEP
Approved
Completed
Awarded
100%
Fall 2028
#022 Queen Elizabeth
Secondary
BEP
Approved
In process



#150 Tamanawis
Secondary
BEP
Approved
In process










SUPPORTED PROJECTS (Pending Ministry of Education Funding Approval)
20-Classroom
Addition
Pending




#175 Clayton Heights
Secondary
20-Classroom
Addition
Pending




#183 Forsyth Road
Elementary
8-Classroom
Addition 
Pending




*This column represents the percentage of the contract value that has been paid out to the contractor.

Design Stage

Following approval of the funding agreement with the Ministry of Education, the design stage begins.
Sketch plans/schematic design is the preliminary design concept. The sketch plan then advances a more detailed design, used to secure City of Surrey development/building permits. These designs are included in the bid tender package.

Tender Stage

When a project's design is complete, it is put to tender. Construction firms bid for the contract agreement to perform the work.

Construction Stage

After the project has been awarded to the successful bidder, construction can begin. This stage has many varying factors that affect the amount of time required to finish a project.

Occupancy Stage

In this stage the new development is ready to be furnished, fit and occupied. While the building is now being used as planned, minor work continues.