Progress Chart
[ Current Projects | Completed Projects | Future Projects ]
Approved Projects
A project is considered approved once Ministry of Education and Child Care funding is committed. Normally, a public announcement by the Ministry of Education indicates support to prepare and submit a Project Definition Report (PDR). The projects on this list have received the funding required to proceed into design and construction.
- The completion/occupancy dates in this report are target dates only and subject to change as the projects proceed.
- This progress chart is updated following each board meeting.
Site | Description | Approval | Design | Tender Award | Construction Completion* | Projected Student Occupancy |
---|---|---|---|---|---|---|
27-Classroom New School | Apr 6, 2020 | Design Complete | Awarded | 90% | Jan 2025 | |
8-Classroom Addition | Aug 12, 2021 | Design Complete | Awarded | 50% | May 2025 | |
10-Classroom Addition | Aug 12, 2021 | Design Complete | Awarded | 40% | May 2025 | |
27-Classroom New School | Mar 30, 2021 | Design Complete | Awarded | 19% | March 2026 | |
145 Woodland Park Elementary | 16-Classroom Modular Addition | Sep 27, 2023 | Design Complete | Spring 2024 | In process | Fall 2024 |
12-Classroom | Sep 27, 2023 | Design Complete | Spring 2024 | In process | Fall 2024 | |
055 Lena Shaw Elementary | 8-Classroom Modular Addition | Sep 27, 2023 | Design Complete | Spring 2024 | In process | Fall 2024 |
20-Classroom | Jan 10, 2023 | In process | Spring 2025 | 0% | Fall 2027 | |
047 Guildford Park Secondary | 18-Classroom Addition | May 26, 2023 | In process | Fall 2025 | 0% | Spring 2028 |
23-Classroom Addition | May 9, 2023 | In process | Fall 2025 | 0% | Spring 2028 | |
BUILDING ENVELOPE PROJECTS | ||||||
#022 Queen Elizabeth Secondary | BEP | Approved | In process | Pending | ||
#150 Tamanawis Secondary | BEP | Approved | In process | Pending | ||
SUPPORTED PROJECTS - Pending Ministry Funding Approval | ||||||
20-Classroom Addition | Pending | |||||
20-Classroom Addition | Pending | |||||
8-Classroom Addition | Pending | |||||
37-Classroom New School | Pending | |||||
20-Classroom Addition | Pending | |||||
*This column represents the percentage of the contract value that has been paid out to the contractor.